West Kamloops: Schedule and activities
Project milestones*
Property acquisition | Complete |
Preliminary design | Complete |
Partial site clearing by the city of Kamloops | Complete |
Substation site preparation |
Complete |
Start clearing of trees for the new lines and communications tower |
Complete |
Substation start of construction |
June 2017 |
Start of construction of new lines | Summer 2017 |
Substation in-service | December 2018 |
*Schedule subject to change