Skip to content

Paying your bills during the Canada Post service disruption. Learn more

2023 Bulletin Index - January to April

bulletin test

We periodically post bulletins here to inform customers of developments within BC Hydro Transmission and/or the industry and/or to solicit feedback on policy changes. These announcements can be time sensitive, so please subscribe for the updates.

Stay informed about our bulletins by subscribing for automatic email notifications.

Our Transmission Scheduling bulletins for 2023 are listed below. Select another year to the right to view bulletins from the archive.

View the 2023 bulletins

January to April

Title Bulletin date
OATT Generation Interconnection (GI) Tariff Pages, Order G-304-22 April 25 2023, 3:11 p.m.
System Impact Study and CFS Evaluation Completed April 21 2023, 1:18 p.m.
Amended Business Practices  April 05 2023, 11:40 a.m.
Quarterly Study Metrics Posted April 03 2023, 10:09 a.m.
F2023-F2025 Revenue Requirements Application – Approved F2024 Interim Rate Pages March 31 2023, 9:07 a.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue March 30 2023, 10:03 a.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue March 28 2023, 9:15 a.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue March 23 2023,2:36 p.m.
Amended Long Term Business Practices  March 20 2023, 2:27 p.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue March 14 2023, 12:30 p.m.
Amended Business Practices – Submitting Energy Schedules March 03 2023, 2:09 p.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue February 27 2023, 11:40 a.m.
System Issue February 23 2023, 11:20 a.m.
Impact to Scheduling-Feb 21, 2023 from 10am to 11am PST - Reminder February 21 2023, 9:32 a.m.
Amended Business Practices – Rollover Rights of Long Term Firm Transmission Service February 15 2023, 2:32 p.m.
Impact to Scheduling- Feb 21, 2023 from 10am to 11am PST February 14 2023, 12:03 p.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue February 08 2023, 12:53 p.m.
Amended Business Practices – Conditional Firm Service and Rollover Rights of Long Term Firm Transmission Service February 06 2023, 10:45 a.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue January 23 2023, 4:10 p.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue January 10 2023, 4:25 p.m.
Application to Suspend Obligation to Supply Service to Cryptocurrency Mining Projects January 04 2023, 2:55 p.m.
Quarterly Study Metrics Posted January 03 2023, 4:20 p.m.
Firm Sales to Alberta Long Term PTP Transmission Priority Queue January 03 2023, 4:20 p.m.


System Impact Study and CFS Evaluation Completed

Posted on April 21, 1:18 p.m.

BCHydro has completed the following:

System Impact Study: Long Term Point-To-Point OASIS Request AREF: 98379860, 98379861, 98379862 On the GMS.MCA.REV to BC.US.BORDER Path October 1, 2023 to October 1, 2030.

CFS Evaluation: Evaluation of Conditional Firm Service (CFS) AREFs: 98379860, 98379861, and 98379862 On the GMS.MCA.REV to BC.US.BORDER Path.

Please click here to view the reports. 


Amended Business Practices

Posted on April 05, 11:40 a.m.

Further to BC Hydro’s bulletin on March 3, 2023, BC Hydro updated Processing of LTFPTP TSR, Conditional Firm Services and Submitting a LTFPTP TSR business practices, and have posted them on our Business Practices webpage.


Quarterly Study Metrics Posted

Posted on April 03, 10:09 a.m.

The quarterly study metrics for January 1, 2023 to March 31, 2023 has been posted. This, and previous study metrics can be viewed at the study metrics page.


F2023-F2025 Revenue Requirements Application – Approved F2024 Interim Rate Pages

Posted on March 31, 9:07 a.m.

Further to the bulletin posted on September 8, 2021, BC Hydro filed the attached tariff sheets reflecting the interim rates for fiscal 2024 in accordance with Commission Order Nos. G-59-23 and G-60-23, on March 29, 2023, for OATT Attachment H, Schedule 00, Schedule 01, and Schedule 03.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on March 30, 10:03 a.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on March 28, 9:15 a.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on March 23, 2:36 p.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Amended Long Term Business Practices 

Posted on March 20, 2:27 p.m.

BC Hydro amended Processing of LTFPTP TSR, Conditional Firm Services and Submitting a LTFPTP TSR business practices, which further clarifies queue processing language. Please provide comments to Brenda Ambrosi by April 4, 2023; customer comments may be posted. 


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on March 14, 12:30 p.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Amended Business Practices – Submitting Energy Schedules

Posted on March 03, 2:09 p.m.

BC Hydro amended the Submitting Energy Schedules business practice by adding section 14.0, “Other Conditions”, which clarifies conditions on certain e-Tag creation practices. Please provide comments to Brenda Ambrosi by March 17, 2023; customer comments may be posted.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on February 27, 11:40 a.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


System Issue

Posted on February 23, 11:20 a.m.

We are currently experiencing validation issues in our MODS system. We are looking into it and appreciate your patience regarding this matter.


Impact to Scheduling-Feb 21, 2023 from 10am to 11am PST - Reminder

Posted on February 21, 9:32 a.m.

Further to the bulletin posted on February 14, on February 21, 2023 between 10:00 am to 11:00 am PST, BC Hydro will be updating one of its business systems (MODS) in the Production environment.  Thus, there will be an impact to scheduling during this outage window.  Consequently, BC Hydro asks its OATT customers to schedule around this outage time period. Please contact Brenda Ambrosi at 604-312-7391 if you experience any issues.


Amended Business Practices – Rollover Rights of Long Term Firm Transmission Service

Posted on February 15, 2:32 p.m.

BC Hydro added clarifying language to the Rollover Rights of Long-Term Firm Transmission Service business practice with regards to Section 2.0, “Evaluation of Initial Requests”.


Impact to Scheduling-Feb 21, 2023 from 10am to 11am PST    

Posted on February 14, 12:03 p.m.

On February 21, 2023 between 10:00 am to 11:00 am PST, BC Hydro will be updating one of its business systems (MODS) in the Production environment.  Thus, there will be an impact to scheduling during this outage window.  Consequently, BC Hydro asks its OATT customers to schedule around this outage time period. Please contact Brenda Ambrosi at 604-312-7391 if you experience any issues.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on February 08, 12:53 p.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Amended Business Practices – Conditional Firm Service and
Rollover Rights of Long Term Firm Transmission Service

Posted on February 06, 10:45 a.m.

BC Hydro updated the following two business practices. The amended language are indicated by vertical lines on the right margin of each business practice, respectively:

Conditional Firm Service – Updated Section 9.0, Biennial Reassessment

Rollover Rights of Long-Term Firm Transmission Service - Updated language to be consistent with BCUC order G-304-22


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on January 10, 4:10 p.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on January 10, 4:25 p.m

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.


Application to Suspend Obligation to Supply Service to Cryptocurrency Mining Projects

Posted on January 4, 2:55 p.m.

On December 21, 2022, BC Hydro filed an application with the British Columbia Utilities Commission (BCUC) requesting the BCUC suspend its obligation to supply service to certain new cryptocurrency mining projects (Application).  On December 21, 2022, the Lieutenant Governor in Council issued Order in Council (OIC) 692 directing the BCUC to issue final orders approving BC Hydro’s Application. On December 28, 2022, the BCUC, via Order G-390-22 A, approved relief of obligations to BC Hydro.  The suspension to supply service will be temporary and last 18 months from the date of BCUC’s order approving the Application.


Quarterly Study Metrics Posted

Posted on January 3, 4:20 p.m.

The quarterly study metrics for October 1, 2022 to December 31, 2022 has been posted. This, and previous study metrics can be viewed at the study metrics page.


Firm Sales to Alberta Long Term PTP Transmission Priority Queue

Posted on January 3, 4:20 p.m.

The Firm Sales to Alberta Long Term PTP Transmission Priority Queue has been revised. Previous version of the updates can be viewed at Archived LTPTP Transmission Queue Updates.